Monday 25 August 2014

Final Walkthrough

We finally got our walk through out of the way!
There were more delays then expected in the last couple of months getting trades to return for finishing touches on the Garage, getting the concreting of the back stairs done and in particular waiting for Castle Railing to install our balcony balustrade.
At the time of our walk through some things still weren't done:

  • Painters needed to paint the garage, complete the external façade & the stair rails
  • Electricians needed to connect the power & finish the external lights
  • Silicon needed doing in all the bathrooms
  • Water Tank was not yet delivered or installed

Besides these few things the house was looking fantastic and only a few painting touch-ups were noted during our walk through.

We booked our Handover feeling very excited that we would finally be picking up our keys. However, there is still one setback to overcome...

It wasn't the painters - They turned up and completed the painting.
Photo of our beautiful façade below:



It wasn't the silicon on the sinks - That was done on Saturday.
The water tank has been delivered (though we are waiting for a gas pipe to be moved that is in the way)



Still waiting on the electrician but that was no surprise LOL (We have been trying to get the power connected all month...)